O'Callaghan v. State of Illinois

5 Ill. Ct. Cl. 206 Illinois Court of Claims Filed 1925-05-20 No. 903
Disposition: (No. 903-Claimant awarded $4,273.20.) Award: $4,273.20 Agency: Research and Educational Hospital of the State of Illinois
Cite as: O'Callaghan v. State of Illinois, 5 Ill. Ct. Cl. 206 (1925)
Legacy General 5 awarded 1920s O'Callaghan v. State of Illinois 5 Ill. Ct. Cl. 206 1925-05-20 (No. 903-Claimant awarded $4,273.20.) /opinions/v05-p0226-2/

EDWARD O'CALLAGHAN AND HENRY O'CALLAGHAN, PARTNERS, Claimant, v. STATE OF ILLINOIS, Respondent.

Case summary

Claimants, plumbing contractors, sought $7,192.30 for extra work and materials ordered beyond their original contract for the Research and Educational Hospital. The court awarded $4,273.20, the amount admitted by the State's building department and consented to by the Attorney General.

Claim type: Contract

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. CONTRACT-when State liable. Where a contract has been made between claimant and the State for certain work, and the contract is performed by claimant, according to its term, and the contract price is paid, but during the progress of the work the State through its authorized agent orders certain specific work to be performed not stipulated in the contract and such additional work is performed and material furnished for same, claimant is entitled to compensation for such additional material furnished and work performed.

Claimants, Edward O'Callaghan and Henry O'Callaghan, partners, doing business under firm name and style of O'Cal[*207]Inghan Brothers, claim $7,192.30 as disclosed by the statement of their claim, and as shown by the evidence.

The claimants are plumbers and contractors, and as such, on to-wit: the 20th day of November, A. D. 1922, entered into a contract with the State of Illinois by its proper officers to do certain work, to-wit: Plumbing for a building shown as the Research and Educational Hospital of the State of Illinois, in Chicago, Illinois, under a contract of $145,000.00. The contract was completed and said contract price paid. However during the progress of the work, the State by its said duly authorized agents ordered other certain specific work performed in addition to that stipulated in the contract, and materials also to be furnished and added by claimants which they did as directed, and for which they charge the State the sum of $7,192.30. This bill was presented to the State's building department and upon an investigation and analysis of same by the proper officers of said department, they admitted the correctness of the claim, less $2,919.10, and agreed that the State should pay them the sum of $4,273.20.

The Attorney General has investigated the matter also and consents to allowance of said last named sum. From the weight of the evidence in the case it seems that claimants are entitled to said sum last aforesaid. The court accordingly awards the claimants the sum of $4,273.20.

Official volume 5 (Containing cases in which opinions were filed between July 1, 1923–June 30, 1927)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.