E. J. ALBRECHT COMPANY, Claimant, v. STATE OF ILLINOIS, Respondent.
Case summary
Claimant sought damages for expenses incurred when the State cancelled a road construction contract after the Prevailing Wage Law was held invalid. The court awarded the stipulated settlement amount of $2,365.27.
AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.
Headnotes
- CONTRACTS-work performed and materials furnished under contract, cancelled before completion because of invalidity of law under which awarded -damages-stipulation-when award may be made. An award is made herein on the authority of Bishop Construction Co., No. 1845, ante.
This is a suit brought by the claimant, E. J. Albrecht Company, a corporation of the City of Chicago, County of Cook, State of Illinois, against the defendant, State of Illinois, to recover damages caused by the cancellation of road construction contract No. 4549, on State Bond Issue Route No. 46, Section 462-V-B awarded on the 16th day of September, 1931.
The facts in this case are as follows: That after the complainant commenced performance under the said contract it received a notice from the respondent on the 6th day of October 1931, through its Division of Highways, Department of Public Works and Buildings, that no payments could be made for work done under the contract for the reason that the "Prevailing Wage Law" under which the contracts had been let was held to be invalid and void by the courts of the State and that in the event the claimant proceeded to go further under the said contract, it did so at its own peril. After this notice was received complainant's forces and machinery remained idle from October 6th to November 2nd, 1931, thereby necessitating considerable expense for which the claimant asked damages, and the State was then and there so notified.
Thereupon the Division of Highways, Department of Public Works and Buildings, of the State of Illinois, through its Director and Chief Highway Engineer, reached an agreement in settlement of the damages caused as aforesaid, and stipulated to make payment in the sum of $2,365.27. The Attorney General has approved of the said settlement and stipulation, [*44] but the Division of Highways could not pay the claim and therefore recommended that a claim be filed with this court.
As there is no dispute as to the facts presented in the claimant's declaration and the evidence establishes the claimant's right of action, the court is of the opinion that the claim is reasonable and should be paid. The court accordingly awards the claimant the sum of $2,365.27.