McCarthy Improvement Company v. State of Illinois

7 Ill. Ct. Cl. 53 Illinois Court of Claims Filed 1931-12-08 No. 1863
Disposition: (No. 1863-Claimant awarded $58,508.27.) Award: $58,508.27 Agency: Division of Highways, Department of Public Works and Buildings
Cite as: McCarthy Improvement Company v. State of Illinois, 7 Ill. Ct. Cl. 53 (1931)
Legacy General 7 awarded 1930s McCarthy Improvement Company v. State of Illinois 7 Ill. Ct. Cl. 53 1931-12-08 (No. 1863-Claimant awarded $58,508.27.) /opinions/v07-p0071-1/

McCarthy Improvement Company, Claimant, v. State of Illinois, Respondent.

Case summary

Claimant sought damages for cancellation of road construction contracts after the prevailing wage law was held invalid. The court awarded the stipulated settlement amount of $58,508.27.

Claim type: Contract

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. Contracts-work performed under contract, cancelled before completion, because of invalidity of law under which awarded-stipulation-when award may be made thereon. An award is made herein on authority of Bishop Construction Co. vs. State, No. 1848, ante.

This is a suit brought by the claimant, McCarthy Improvement Company, a corporation, of the City of Davenport, County of Scott, State of Iowa, against the defendant, State [*51] of Illinois, to recover damages caused by the cancellation of road construction contracts Nos. 4547, 4550, 4551, 4554, 4554, 4588 and 4589, on the State Bond Issue Route No. 83, Sections 103 and 104; Route No. 97, Section 142-A; Route No. 148, Sections 106 and 107, awarded on the 16th day of September, 1931, and Route 77, Sections 105-W and 105-W-1, awarded on the 21st day of September, 1931.

The facts in this case are as follows: That after the complainant commenced performance under the said contracts it received a notice from the respondent on the 6th day of October, 1931, through its Division of Highways, Department of Public Works and Buildings, that no payments could be made for work done under the contracts for the reason that the "Prevailing Wage Law" under which the contracts had been let was held to be invalid and void by the courts of this State and that in the event the claimant proceeded further under the said contracts, it did so at its own peril. When this notice was received the complainant had already completed work under the contract costing $12,097.25, and thereafter complainant's forces and machinery remained idle from October 6th to November 2nd, 1931, thereby necessitating considerable expense in addition to the cost of work completed, for which the claimant asked damages, and the State was then and there so notified.

Thereupon, the Division of Highways, Department of Public Works and Buildings, of the State of Illinois, through its Director, and Chief Highway Engineer, after asking deductions for cement sacks salvaged reached an agreement in settlement of the damages caused as aforesaid and stipulated to make payment in the sum of $58,508.27. The Attorney General has approved of the said settlement and stipulation but the Division of Highways could not pay the claim and therefore recommended that a claim be filed with this court.

As there is no dispute as to the facts presented in the claimant's declaration and the evidence establishes the claimant's right of action, the court is of the opinion that the claim is reasonable and should be paid. The court accordingly awards the claimant the sum of $58,508.27.

Official volume 7 (Containing cases in which opinions were filed between July 1, 1931–June 30, 1933)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.