Illinois Court of Claims Opinions
Legacy General
Download PDF

Charles O. McCay and William A. Hasse v. State of Illinois

21 Ill. Ct. Cl. 90 Illinois Court of Claims Filed 1951-10-06 No. 4404
Disposition: (No. 4404-Claim denied.) Agency: Department of Public Works and Buildings
Cite as: Charles O. McCay and William A. Hasse v. State of Illinois, 21 Ill. Ct. Cl. 90 (1951)
Legacy General 21 denied 1950s Charles O. McCay and William A. Hasse v. State of Illinois 21 Ill. Ct. Cl. 90 1951-10-06 (No. 4404-Claim denied.) /opinions/v21-p0118-1/

CRARLES 0. MCCAYAND WILLIAM A. HASSE, doing business as McCay and Hasse, Claimants, v. STATE OF ILLINOIS, Respondent,. Opinion Pled October 6, 1951.

Case summary

Claimants sought damages for delay caused by another contractor on a grade separation project. The court denied the claim, holding that the contract's standard specifications, which required each contractor to assume liability for delays caused by other contractors, barred recovery, and that the equitable test was abolished by the 1945 Court of Claims Act.

Claim type: Contract

Statutes cited: Ill. Rev. Stat., 1949, Chap. 37, Secs. 439.1-439.24

Cases cited: Illinois Steel Bridge Co. vs. State, 7 C.C.R. 75

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. C o NTR a m s ~ h e nextra compensation will not be dlowed under. Where contract, signed by claimant, incorporated Article 5.7 of the Standard Specificatioils for Road and Bridge Construction, which Article saves the State harmless from any damages caused by delays, claim for extra compensation will be denied.

Claimants, Charles 0. McCay and William A. Hasse, doing business-as McCay and Hasse, filed their complaint in which they seek to recover damages for delay in connection with a grade separation contract between claimants and respondent acting through the Department of Public Works and Buildings. Respondent has filed a motion to dismiss.

In November, 1946, claimants’ proposal to perform certain grade separation work in Cook County near 159th Street and Laramie Avenue was accepted by respondent, and a written contract was entered into. The contract price was slightly over $200,000.00.

At about the same time respondent entered into another contract with the Chicago, Rock Island and Pacific Railroad Company to perform certain other work in connection and conjunction with claimants’ work. The Railroad Company was over a year late in doing what it was supposed to do, and claimants were delayed on that account.

Claimants allege that, by reason of the extra year’s delay, they had to pay higher wages, and higher prices for materials to their damage in the sum of $30,633.94, and they further allege that no part of the delay was due to claimants’ derelictions.

The contract entered into between claimants and respondent is attached to the complaint. Several provisions of the proposal leading up to the contract, found on pages 2, 4 and 6 thereof, preclude extra compensation.

Under Paragraph No. 3 of the document entitled “Contract”, it is provided, among other things, that the “Standard Specifications for Road and Bridge Construction”, dated July 1, 1942, is an essential document [*92] of the contract between the claimants and respondent, and is made a part thereof. (Claimants’ exhibit “A”;, page 37.) Article 5.7 of the Standard Specifications for Road and Bridge Construction, adopted July 1 , 1942, provides in part as follows:

* * * * * *

Il* $

Each contractor involved shall assume all liability, financial or otherwise, in connection with his contract and shall protect and save harmless the Department from any and all damages or claims that may arise because of inconvenience, delay, or loss experienced by him becsuse of the presence and operations of other contractors working within the limits of the same project, and he shall assume an responsibility for all work not completed or accepted because of the presence and operations of the other contractors.

* * * * w,

* * *

In Illinois Steel Bridge Co. vs. State, 7 C.C.R. 75, this Court construed a contract provision almost iden- , tical with the above quoted provision from Standard Specifications, and held that such provision relieved the State of any liability for damages caused by delays of another contractor with the State. This decision binds us in this case.

We might also mention that the “equity and good conscience’’ test, which was used in certain cases cited by claimants, was abolished by the 1945 Court of Claims Act. Ill. Rev. Stat., 1949, Chap. 37, Secs. 439.1- 439.24.

The motion of respondent to dismiss is sustained, and the case is hereby dismissed.

Official volume 21 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion between: July 1, 1951–April 30, 1954)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.