Illinois Court of Claims Opinions
Legacy General
Download PDF

Commercial Light Company v. Fillinois

26 Ill. Ct. Cl. 443 Illinois Court of Claims Filed 1969-04-17 No. 5514
Disposition: (No. 5514-Claimant awarded $19,898.92.) Award: $19,898.92 Agency: Department of Public Works and Buildings
Cite as: Commercial Light Company v. Fillinois, 26 Ill. Ct. Cl. 443 (1969)
Legacy General 26 awarded 1960s Commercial Light Company v. Fillinois 26 Ill. Ct. Cl. 443 1969-04-17 (No. 5514-Claimant awarded $19,898.92.) /opinions/v26-p0484-1/

COMMERCIAL LIGHT COMPANY, ACORPORATION, Claimant, v. STATE O FILLINOIS, Respondent.

Case summary

Claimant sought $42,925.00 for additional costs due to delays caused by another prime contractor on a state construction project. The court awarded $19,898.92 based on a stipulation between the parties.

Claim type: Contract

Cases cited: Kaiser vs. State of Illinois, 7 C.C.R. 99; Divane Bros. Electric Co. A Corporation vs. State of Illinois, 22 C.C.R. 546

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. CONTRACTS-where evidence showed t h a t contractor was prevented from completion of his work by reason of delay of general contractor, resulting in loss to sub-contractor, wholly without, his fault, a n award will be made in the absence of contractual agreement to the contrary.

Claimant corporation filed its complaint for the sum of $42,925.00, which it claimed represented additional costs incurred in the execution of a contract entered into with the Department of Public Works and Buildings in March, 1964, for electrical work at the Diagnostic Hospital, Tinley Park State Hospital, Tinley Park, Illinois.

The parties, have submitted a stipulation, which provides, in part, that claimant entered into the above mentioned contract in the net amount of $139,274.00 for the complete electrical work for the Diagnostic Hospital ; that the contract required claimant to work “ In progress with General Work and work of other contractors engaged on the project,’; that the contractor for General Work agreed in its contract to complete construction within 370 days after date of notification of award; that due to material experimentation and other unforseen difficulties in enforcing and meeting contractual quality requirements on the part of all contractor:;, the contractor for General Work was not certified as completed until March of 1967, although claimant could reasonably have anticipated completion on or about April 1, 1966; that claimant’s work was thus delayed being dependent on the General Work Contractor.

The stipulation further states that “respondent, in the absence of a contractual agreement to the contrary, has bccn held liable for such a delay occasioned by one prime contractor to another. Kaiser vs. ,State of Illinois, [*445] 7, C.C.R. 99; Divane Bros. Electric Co. A Corporatiow, vs.

State of Illinois, 22 C.C.R. 546''.

The parties have agreed as to the amount of loss incurred by claimant, as follows:

“It is further stipulated by and between the parties by their respective attorneys that the filing of the briefs and abstracts and all notices with respect thereto be and the same are hereby waived, and that a judgment order be entered in the amount of Nineteen Thousand Eight Hundred Ninety Eight Dollars and Ninety Two Cents ($19,898.92) in favor of claimant and against respondent.”

The stipulation is signed by Attorney General William J. Scott and the attorneys for claimant.

There being no further question to be determined by this Court, claimant is hereby awarded the sum of $19,898.92.

Official volume 26 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion between: January 10, 1967–June 20, 1969)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.