General Claims 27 Awarded 1960s Tuscola Builders Supply Company v. Illinois Department of Public Works et al. 27 Ill. Ct. Cl. 28 November 11, 1969 Awarded $426.09 1969-11-11 426 2700028 /opinions/v27-p0042-1/
TUSCOLA BUILDERS SUPPLY COMPANY, Claimant, v. STATE OF ILLINOIS, DEPARTMENT OF PUBLIC WORKS AND BUILDINGS, DIVISION OF HIGHWAYS, Respondent.
Case summary
Claimant sought payment for goods or services provided under a contract, but the appropriation from which the claim should have been paid had lapsed. The court awarded the amount due, $426.09, because the claim was valid and the appropriation had lapsed.
Claim type: Lapsed Appropriation
AI-generated summary from the opinion text — may contain errors. The opinion
text and PDF above are the official record.
Headnotes
- CoNTRAcrs-hpsed appropriation. When the appropriation from which a claim should have been paid has lapsed, the Court will enter an award for the amount due claimant.
BUILDEMSUPPLY COMPANY, Claimant, pro se. TUSCOLA WILLIAM J. SCOTT, Attorney General; LEE D. MARTIN, Assistant Attorney General, for Respondent.
BOOKWALTER, J.
The official report prints no opinion text for this claim beyond the heading, headnote,
and judge line shown above. The Court's disposition is stated in the heading. See the
PDF for the page as printed.
Official volume 27 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion between: July 1, 1969–June 30, 1972)
·
All opinions in this volume
·
Also on CourtListener
This text is OCR/derived from the official volume and may contain errors. The
PDF is authoritative. Boundary pages shared with the adjacent
opinion are reproduced whole, so the page image may show a neighbor's opening or
closing lines; the transcript text itself is opinion-scoped. See
About & sources.
Report an error in this opinion