Springfield Van and Storage Company v. State of Illinois

34 Ill. Ct. Cl. 220 Illinois Court of Claims Filed 1980-04-30 No. 80-CC-0841
Disposition: (No. 80-CC-0841-Claimant awarded $3,963.12.) Award: $3,963.12
Cite as: Springfield Van and Storage Company v. State of Illinois, 34 Ill. Ct. Cl. 220 (1980)
General Court of Claims 34 awarded 1980s Springfield Van and Storage Company v. State of Illinois 34 Ill. Ct. Cl. 220 1980-04-30 (No. 80-CC-0841-Claimant awarded $3,963.12.) /opinions/v34-p0320-1/

SPRINGFIELD VAN AND STORAGE COMPANY, Claimant, u. THE STATE OF ILLINOIS, Respondent.

Case summary

Claimant sought payment for moving services under a contract with a $20,000 limitation. The court initially awarded $1,135.27, but upon stipulation vacated that order and entered an amended award of $3,963.12.

Claim type: Contract

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. CONTRACTS-award granted for contractual moving services. The Claimant was granted an award for the amount of money due for services involving office moving, as the services performed were the result of delays caused by Respondent’s failure to have the new facilities prepared for the move.

This matter comes before the Court upon motion of Respondent to dismiss and Claimant’s objections to said motion.

Respondent’s motion to dismiss is based on the premise that Claimant’s claim exceeded the limitation of the contract amount. The contract had a $20,000.00 limitation figure. Prior to June 1, 1979, the limitation had not been exceeded and there was approximately $1,921.92remaining unspent out of the total contract amount.

During the month of June, five separate and distinct moves were made by Claimant on behalf of Respondent in the total amount of $786.65. As of June 27, 1979, a balance remained on the contract amount of $1,135.27.

On June 28, 1979, Claimant was requested to move some furniture over a weekend for the Department of Public Aid, a move which if it had occurred as stated, would have involved less than $1,000.00 and been within the limitations of the contract and the appropriations (on which $1,135.27 remained). Claimant loaded the moving trucks and it was then determined that the carpet was not finished, elevators which Claimant had been informed would be available were not available, and considerable overtime was involved, which raised costs from $l,OOO.OO to $3,045.96.

The record discloses that the delay was caused not by Claimant but by the Respondent and that had Claimant not provided the services it did provide, service would have been disrupted.

[*222] The Court finds that the amount remaining unpaid on the contract amount is $1,135.27.

It is hereby ordered:

That an award in the amount of $1,135.27 be entered in favor of Claimant.

ORDER ON MOTION TO VACATE AND AMEND HOLDERMAN, J.

This matter comes before the Court upon stipulation to vacate order heretofore entered and entry of an amended order, a copy of which stipulation is attached to this order.

An order was entered by this Court on April 30, 1980,granting an award to Claimant in the amount of $1,135.27. Respondent's stipulation states that said order should be vacated and that the correct amount due Claimant is $3,963.12.

It is hereby ordered:

Motion to vacate order previously filed by Claimant is granted and a new award is hereby entered in favor of Claimant in the amount of $3,963.12.

Official volume 34 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion for: Fiscal Year 1981 – July 1, 1980–June 30, 1981)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.