HENSONROBINSON COMPANY, Claimant, 2). THE STATE OF ILLINOIS, Respondent.
Case summary
The claimant sought damages for additional labor costs caused by a one-year construction delay solely attributable to the respondent. The court awarded $3,536.00 based on the respondent's stipulation.
AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.
Headnotes
- TYRONE C. FAHNER, Attorney General (WILLIAM E. WEBBER, Assistant Attorney General, of counsel), for Respondent.
- STiPuLATIoNs-additional hbor costs-delay by State. Award granted for additional labor costs incurred by Claimant in connection with construction project as parties stipulated that State was cause of delay resulting in damages to Claimant.
This cause coming on to be heard on the Respondent’s stipulation and the Court being fully advised in the premises finds that this is a claim for damages arising from a delay in construction caused solely by the Respondent. The Respondent has stipulated that the Claimant had nothing to do with the delay and the Claimant was damaged in the amount of $3,536.00 as the result of additional labor costs caused by the delay of approximately one year. The supplemental departmental report shows that funds were available had they been properly utilized.
It is therefore ordered, in accordance with the Respondent’s stipulation, that this Claimant be granted an award in the amount of $3,536.00.