Illinois Court of Claims Opinions
General Court of Claims
Download PDF

Fidelity Deposit Company of Maryland v. State of Illinois

37 Ill. Ct. Cl. 212 Illinois Court of Claims Filed December 13,1984 No. 82-CC-2244
Disposition: (No. 82-CC-!2%4-Claim denied.) Agency: Capital Development Board
Cite as: Fidelity Deposit Company of Maryland v. State of Illinois, 37 Ill. Ct. Cl. 212 (1984)
General Court of Claims 37 denied 1980s Fidelity Deposit Company of Maryland v. State of Illinois 37 Ill. Ct. Cl. 212 December 13,1984 (No. 82-CC-!2%4-Claim denied.) /opinions/v37-p0294-1/

FIDELITY DEPOSIT COMPANY OF MARYLAND, Claimant, TI. THE STATE OF ILLINOIS, Respondent.

Case summary

Claimant sought $5,500 for additional dewatering expenses under a construction contract. The court denied the claim because all appropriated and released funds had been expended, despite noting that funds had previously been available but were cancelled.

Claim type: Contract

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. NEIL F. HARTIGAN, Attorney General (ERIN M. O’CONNELL, Assistant Attorney General, of counsel), for Respondent .
  2. CoNTuAcTs-phmbing work-extras-all funds expended-claim denied. The Claimant’s action,’seeking recovery for the extra work done
  3. III when its plumbing project for a new school encountered an unanticipated high water table and running sand, was denied, notwithstanding a stipulation of the parties providing for payment of the claim, since all the funds appropriated and released for the project had been expended through other payments and the Goyernor’s cancellation of remaining released funds.

This claim is before the Court on the joint 1 stipulation filed by the parties on November 7, 1983. By I order of this Court dated January 5, 1984, the case was I continued until submission of additional information by the ’ Respondent. ‘That information was provided September 12, 1984. The case is now before us for decision.

The parties stipulated as follows: I

I

1. Claimant is a bonding company which pursuant to its bond became the contractor of record for plumbing work completed at New Sycamore Junior High School, Sycamore, Illinois.

2. Claimant hired Great Lakes Plumbing and Heating Company to perform the contract work.

3. In the course of completing the work, Great Lakes encountered conditions not anticipated in the

I

original contract, namely a high water table and running I sand. I

I

4. These conditions necessitated renting dewater- I ing equipment so that the plumbing work could be I completed.

5. Claimant and Respondent have agreed that the I amount of Claimant’s claim for the additional expense of the equipment rental is $5,500.00.

6. The parties agree that Claimant should be awarded $5,500.00 as a complete satisfaction of Claimant’s claim. I [*214]

, 214

This Court is not bound by such settlements, but neither does it seek to interpose a controversy where none appears to exist. We encourage settlement where the case warrants it and will not reject a settlement out of hand. Although this settlement appears fair and reasonable and entered into at arms length we unfortunately are constrained by operation of law to reject the settlement and deny the claim.

The additional information elicited by our order of January 5, 1985, reveals that all funds appropriated by the legislature and released by the Governor have been expended. For this reason we are unable to acquiesce in making an award. We do note for the record however that on July 26, 1978, the director of the Capital Development Board (the Respondent herein) requested, the director of the Bureau of the Budget recommended, and the Governor approved, a cancellation of released funds in the amount of $16,210.00 for the stated purpose that the contracts awarded for the project plus contingencies were less than the amount of funds released, and that therefore that amount of money was not required. We further note for the record that on June 23,1981, the Director of the Capital Development Board requested, the director of the Bureau of the Budget recommended, and the Governor approved another cancellation of released funds in the amount of $40,531.00 for the stated purpose that the project was complete. Thus, it appears at one time there were more than sufficient funds appropriated and released to have covered this settlement but due to the events described above their release was cancelled.

Claim denied.

Official volume 37 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion for: Fiscal Year 1985 – July 1, 1984–June 30, 1985)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.