Illinois Court of Claims Opinions
General Court of Claims
Download PDF

Wil-Freds v. State of Illinois

38 Ill. Ct. Cl. 152 Illinois Court of Claims Filed 1985-11-18 No. 81-CC-1602
Disposition: (No. 81-CC-1602-Claimant awarded $82,000.00.) I Award: $82,000.00 Agency: Capital Development Board
Cite as: Wil-Freds v. State of Illinois, 38 Ill. Ct. Cl. 152 (1985)
General Court of Claims 38 awarded 1980s Wil-Freds v. State of Illinois 38 Ill. Ct. Cl. 152 1985-11-18 (No. 81-CC-1602-Claimant awarded $82,000.00.) I /opinions/v38-p0234-1/

WIL-FREDS, INC., Claimant, 2). THE STATE OF ILLINOIS, Respondent.

Case summary

Claimant sought damages for breach of contract due to delay in making the project site available, resulting in increased costs. The court entered judgment on stipulation awarding $82,000.00.

Claim type: Contract

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. O'HALLORAN, NEIL F. HARTIGAN, Attorney General (ERIN M. O'CONNELL, Assistant Attorney General, of counsel), for Respondent.
  2. CoNTRAcrs-school construction delayed-State at fault-stipuhtwnclaim awarded. A contractor involved in the construction of a school was kept from completing the work in a timely manner because the State failed to make the project site available, and pursuant to a stipulation resulting from arms-length bargaining, an award was granted the contractor to cover the increased costs associated with the performance of the work under the contract after the delay.

This cause comes before this Court on a stipulation for the entry of judgment submitted by the parties. This [*153] is a breach-of-contract claim arising out of the construction of the West Pullman Nansen Elementary School (the “project”) in Chicago, Illinois.

The overall project consisted of three sequential phases, each being the subject of a separate contract with the Capital Development Board (the “CDB”). Claimant was the Phase 111 contractor. Because the phases were sequential, Claimant could not commence its Phase I11 work until the first two phases were completed. I

On October 4, 1978, Claimant received authorization from CDB to proceed with Phase I11 contract work at the project. Pursuant to the contract, Claimant was to complete its work within 330 days as measured from the date of the notice of award of the contract, August 22, 1978. This established a July 17, 1979, completion date for Claimant for its work on the project. Except for , some minor change order work done in February 1979, Claimant could not commence its work until March 20, 1979. It is this delay between’october 1978, and March 1979, that has given use to the claim herein.

I

In its amended complaint, Claimant alleged that 1 CDB breached the contract through its failure to make the project site available to Claimant in a timely manner

I

such that Claimant could perform its work within the time contemplated by the parties at the time of bidding. As a result of this delay, Claimant has alleged that it suffered damages in the amount of $128,030.00 associated with its increased cost of performance of its work under the contract.

After extensive review of Claimant’s supporting records by representatives of CDB and following lengthy negotiations between the parties, CDB has stipulated and agreed that Claimant was prevented from [*154]

i

I

proceeding with its work on a timely basis and, for purposes of this claim only, admits liability under the amended complaint.

Because of the time and expense of trial and the vagaries of proof associated with this type of claim, the parties have stipulated and agreed that judgment should be entered in Claimant’s favor in the amount of $82,000.00.

Although this Court is not bound by any stipulation, it is not the practice of this Court to interpose controversy between the parties where none seems to exist. The instant stipulation appears to have been entered into after careful consideration of the facts and applicable law by authorized representatives of the parties regarding delay damage claims under State construction contracts. The amount agreed upon seems to have resulted from the give and take associated with arms-length bargaining. This being the case, this Court sees no reason not to honor the stipulation of the parties.

It is hereby ordered that Claimant, Wil-Freds, Inc., be awarded the sum of eighty-two thousand and 00/100 ($82,000.00) dollars in full and complete satisfaction of all its claims herein.

Official volume 38 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion for: Fiscal Year 1986 – July 1, 1985–June 30, 1986)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.