Illinois Court of Claims Opinions
General Court of Claims
Download PDF

Dipaolo Company and Rossetti Contracting Co. v. State of Illinois

38 Ill. Ct. Cl. 290 Illinois Court of Claims Filed Unknown No. 85-CC-2436
Disposition: (No. 85-CC-2436-Claim dismissed.)
Cite as: Dipaolo Company and Rossetti Contracting Co. v. State of Illinois, 38 Ill. Ct. Cl. 290
General Court of Claims 38 dismissed Dipaolo Company and Rossetti Contracting Co. v. State of Illinois 38 Ill. Ct. Cl. 290 Unknown (No. 85-CC-2436-Claim dismissed.) /opinions/v38-p0372-1/

DIPAOLO COMPANY and ROSSETTI CONTRACTING Co., INC., a Joint Venture-No. 7, Claimant, v. THE STATE OF ILLINOIS, Respondent. Order $Zed March 28,1986.

Case summary

Claimant sought damages for breach of a construction contract. The court dismissed the claim because the contract's standard specification required a claim to be filed within 60 days of final payment, and the claim was filed more than three years after final payment was accepted.

Claim type: Contract

Statutes cited: Ill. Rev. Stat. 1983, ch. 37, par. 439.8(b)

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. II CONTRACTS-COWtrUCtiOfl contract-untimely chim denied. The Court

FRANCIS M. DONOVAN, for Claimant.

NEIL F. HARTIGAN, Attorney General (ROBERT J. SKLAMBERG, Assistant Attorney General, of counsel), for Respondent.

[*1] I

I

291 1 II CONTRACTS-COWtrUCtiOfl contract-untimely chim denied. The Court

I

of Claims dismissed a claim arising from a contract for paving and sewer I I work, since the contract included the standard specification providing that I I acceptance of final payment constitutes a release and waiver of any rights

I

l and privileges arising under the contract unless a claim for adjudication is filed within 60 days, and the Claimant did not file its claim until more than three years after accepting final payment.

I

MONTANA, C.J. .

This cause coming on to be heard on the motion of Respondent to dismiss the claim herein; due notice having been given the parties hereto, and the Court I being fully advised in the premises; The Court finds that the instant claim sounds in contract and is brought pursuant to section 8(b) of the Court of Claims Act (Ill. Rev. Stat. 1983, ch. 37, par. 439.8(b)).On March 12,1980, Claimant and Respondent executed the subject contract, No. 34050, for the installation of storm sewers and paving work along Waukegan Road in Deerfield, Illinois. Claimant is alleging that Respondent breached this construction contract.

The contract between Claimant and Respondent

I

included, by reference, the standard specifications for I road and bridge construction, adopted October 1, 1979 (“standard specifications”). Article 109.09 of the standard specifications states: “109.09 Acceptance and Final Payment.

When the State of Illinois is the awarding authority, unless the Contractor files a claim for adjudication by the Court of Claims within 60Ldaysafter acceptance of final payment, the final payment shall constitute a release and waiver of any and all rights and privileges under the terms of the contract, and Shall relieve the Department from any and all claims or liabilities for anything done or furnished relative to the work or for any act or neglect on the part of the Department relating to or connected with the contract.” (Emphasis added.)

I

[*292] We note that final payment for contract No. 34050 was issued to Claimant on January 5, 1982, accepted by Claimant’s bank on January 11, 1982, and paid by the State treasurer on January 12, 1982. The instant claim was filed on March 29, 1985, which is more than three years after Claimant accepted final payment for the contract it had entered into with Respondent.

Clearly, then, Claimant failed to file its claim within the time specified in its contract with Respondent.

Under these circumstances, we are constrained to hold that Claimant is barred from maintaining the instant cause of action in this Court.

It is therefore ordered that Respondent’s motion be, and the same is, hereby granted, and the claim herein is dismissed, with prejudice.

Official volume 38 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion for: Fiscal Year 1986 – July 1, 1985–June 30, 1986)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.