Illinois Court of Claims Opinions
Lapsed Appropriation
Download PDF

Branch-Nicoloff Company v. State of Illinois

40 Ill. Ct. Cl. 252 Illinois Court of Claims Filed 1987-07-09 No. 87-CC-1073
Disposition: (No. 87-CC-1073-Claim denied.) Agency: Northeastern Illinois University
Cite as: Branch-Nicoloff Company v. State of Illinois, 40 Ill. Ct. Cl. 252 (1987)
Lapsed Appropriation 40 denied 1980s Branch-Nicoloff Company v. State of Illinois 40 Ill. Ct. Cl. 252 1987-07-09 (No. 87-CC-1073-Claim denied.) /opinions/v40-p0352-1/

BRANCH-NICOLOFF COMPANY, Claimant, v. THE STATE OF ILLINOIS, Respondent.

Case summary

Claimant sought payment for toilet partition materials provided to Northeastern Illinois University, and the court initially awarded the claim on July 9, 1987, but the legislature did not appropriate funds to pay it. Claimant then sought interest under the Prompt Payment Act, but the court denied the interest claim because the agency's legal ability to pay had ended before delivery was completed.

Claim type: Lapsed Appropriation

Statutes cited: Ill. Rev. Stat., ch. 127, par. 132.401 et seq.

Cases cited: Way-Ken Contractors Supply v. State (1985), 37 Ill. Ct. Cl. 324; OK Electric v. State (1984), 39 Ill. Ct. Cl. 155

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. NEIL F. H ARTIGAN, Attorney General (ROBERT J. S KLAMBERG , Assistant Attorney General, of counsel), for Respondent.
  2. INTEREST-lapsed appropriation claim-interest sought under Prompt
  3. Payment Act- denied. A Claimant filed a standard lapsed appropriation claim for certain materials provided for a State university and the claim was allowed, but the legislature failed to appropriate the required funds and the Claimant sought interest on the unpaid account under the Prompt Payment Act, but that claim was denied, since the Act does not authorize interest on claims in the Court of Claims which would accrue after the responsible agency’s ability to pay had ended, and in the Claimant’s case, the materials were not delivered until after the appropriated funds had lapsed and the agency could not make payment.
  4. STIPULATION S OMMER, J, This is a lapsed appropriation claim. The State agrees to an entry of an award based on the report filed
  5. in this matter which provides the following information: Agency: Board of Governors of State Colleges and Universities Purpose: Toilet partitions for library building restrooms. Fund No. 037-62001-2-25904-3000 Fiscal Year: 1986 Amount: $4,368.00 Claimant’s Social Security or Tax No. 36-0833665 Sufficient funds lapsed to cover this claim.

ORDER

SOMMER, J.

The record in this cause indicates that this is a standard lapsed appropriation claim which should be paid in accordance with the above stipulation. It is so ordered.

ORDER

MONTANA, C.J.

Claimant brought this claim seeking $4,368.00 in payment for toilet partition materials which Claimant provided to the Respondent’s Northeastern Illinois University. In its standard “lapsed appropriation” form complaint Claimant alleged that it demanded payment from Northeastern Illinois University but its demand was refused on the grounds that the funds appropriated for the payment had lapsed.

The Respondent filed a stipulation agreeing that the amount claimed was due and owing and this Court entered the award in favor of the Claimant on July 9, 1987. The bill giving rise to this claim would not have been payable out of a fund which the Court has to pay lapsed appropriation awards. For that reason, this claim [*254] was presented to the legislature in the fall session of 1987. The legislature did not appropriate any funds to pay this claim.

On February 17, 1988, Claimant filed what we interpret to be an amendment to this claim seeking interest on the unpaid account citing the Prompt Payment Act (Ill. Rev. Stat., ch. 127, par. 132.401 et seq.). We have previously ruled that Act does not authorize interest on claims in the Court of Claims which would accrue after the agency’s legal ability to pay has ended. (Way-Ken Contractors Supply v . State (1985), 37 Ill. Ct. C1. 324; OK Electric v. State (1984), 39 Ill. Ct. C1. 155).In this case, satisfactory delivery of the goods was not accomplished until after the funds appropriated for the expenditure had lapsed and the agency was no longer able to make the payment. While we understand that some of the delay in payment has not been caused by the Claimant, the legislature’s postponement of appropriating, or failure to appropriate, funds to pay the award does not change our previous position.

It is hereby ordered that Claimant’s claim for interest be, and hereby is, denied.

Official volume 40 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion for: Fiscal Year 1988 – July 1, 1987–June 30, 1988)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.