Illinois Court of Claims Opinions
Lapsed Appropriation
Download PDF

Carlson Roofing Co. v. State of Illinois

46 Ill. Ct. Cl. 64 Illinois Court of Claims Filed 1997-04-17 No. 84-CC-0595
Disposition: (No. 84-CC-0595-Claimant awarded $11,472.01.) Award: $11,472.01 Agency: Northern Illinois University
Cite as: Carlson Roofing Co. v. State of Illinois, 46 Ill. Ct. Cl. 64 (1997)
Lapsed Appropriation 46 awarded 1990s Carlson Roofing Co. v. State of Illinois 46 Ill. Ct. Cl. 64 1997-04-17 (No. 84-CC-0595-Claimant awarded $11,472.01.) /opinions/v46-p0067-1/

CARLSON ROOFING CO., Claimant, v. THE STATE OF ILLINOIS, Respondent.

Case summary

Claimant sought $14,439.59 as balance due on a roofing contract; $11,472.01 was undisputed but unpaid due to lapsed appropriation. The court awarded that amount but denied the remaining $2,801.58, finding the State entitled to a credit for less expensive substituted materials.

Claim type: Lapsed Appropriation

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. ROLAND W. BURRIS, Attorney General (KATHLEEN O’BRIEN, Assistant Attorney General, of counsel), for Respondent.
  2. LAPSED APPROPRIATIONS-roofing contract-award granted-university entitled to credit for less expensive substituted materials. Pursuant to the parties’ stipulation and request for partial payment, the Claimant roofing company was awarded $11,472.01 in its lapsed appropriation claim arising out of the installation of a replacement roof on a State university building, but the university was entitled to a $2,801.58 credit against the total contract price of over $14,000, since less expensive materials were necessary to meet project guidelines and were substituted by agreement of the parties for materials originally called for in the contract.

ORDER

JANN, J.

This cause comes on to be heard on the Claimant’s request for partial payment and the parties’ joint stipula[*65]tion, due notice having been given, and the Court being advised;

Claimant brought this claim seeking compensation in the amount of $14,439.59 as the balance due on a contract to replace roofing on Cole Hall at Northern Illinois University. The record indicates that a portion of this amount was not paid solely because the funds appropriated for the payment had lapsed. It was stipulated that said portion is $11,472.01, and Claimant has requested payment of this undisputed portion of the claim. Sufficient funds lapsed in appropriation line item number 029-644-01-6-600-0000, FY82, to cover this amount.

We will make an interim award as requested, but because the Court has no appropriation of 029 funds, the payment will have to be made via the Court’s special awards bill.

Accordingly, it is hereby ordered that Claimant be, and hereby is, awarded the sum of $11,472.01, which shall be paid when it becomes available. The balance of the claim remains under litigation.

OPINION

JANN, J.

On June 17, 1982, Claimant, Carlson Roofing Co. (hereinafter referred to as Carlson), entered into a contract with Respondent Northern Illinois University (hereinafter referred to as NIU) for the installation of a replacement roof of a university building. The contract specifically provided in part that Carlson use only materials manufactured by TREMCO Roofing Company and that the project meet Underwriter’s Laboratory (U.L.) class A rating and that TREMCO issue their ten-year guarantee at the project completion.

[*66] After the work on the roof had begun, it was discovered that several amendments to the contract were necessary. The contract price was increased to reflect the additional work and materials required.

It was also discovered that specifications as written could not achieve the U.L. standard required to obtain the TREMCO ten-year guarantee. In order to obtain the U.L. rating, it was necessary to substitute a base sheet material which was $814.98 less expensive than the material originally required, and an insulation which was $1,986.60 less expensive. It must be noted that all undisputed amounts due on the contract have been paid.

The sole issue before this Court is whether or not the State is entitled to a credit of $2,801.58 for the less expensive materials substituted.

It is clear that the purpose of the project specifications as proposed were to offer the bidding contractors a standard on which they could reasonably base their bids. It is reasonable to expect that after a major construction project such as this one has begun, it becomes necessary to make amendments to the original contract agreement.

The evidence indicates Carlson and NIU were agreeable to contract modifications. In fact, the contract price was increased on two separate occasions in the amounts of $2,632.50 and $1,286.39 respectively as additional material and labor became necessary. Carlson was also willing to substitute other less expensive materials when it was determined that the originally specified materials were unsuitable to achieve the ultimate project goals. However, Carlson was not willing to decrease the contract price or credit NIU for the less expensive materials.

Carlson contends that the type of insulation and base sheet were prescribed in the original project specifications [*67] and, therefore, the fact that subsequent changes were required was irrelevant. The fact that two substantially less expensive materials were ultimately required is relevant and NIU is entitled to a credit respectively. In the event that NIU had required a substantially more expensive material, NIU would have been responsible to adjust the contract price to reflect the required change. Clearly, the same standard must apply where a substantially less expensive material is ultimately used.

In absence of any evidence disputing the reduced cost of the substituted materials or any evidence demonstrating that the substitution increased labor or any other costs of construction, we hereby find that NIU is granted a credit to the contract in the amount of $2,801.58 and Carlson’s claim is denied.

Official volume 46 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion for: Fiscal Year 1994 – July 1, 1993–June 30, 1994)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.