Outcome
AwardedAs printed: (No. 5536-Claimant awarded $178.49.)
Award
$178.49
Agency
Department of Public Works and Buildings, Division of Highways
Court
Illinois Court of Claims
Download PDF

KANE COUNTY SERVICE COMPANY, Claimant, vus.. STATE OF ILLINOIS, Respondent.

Case summary

Claimant sought $178.49 for fuel oil delivered to a state facility. The court awarded the amount because the contract was properly entered, services performed, funds available, and the claim was filed after the biennium closed.

Claim type: Lapsed Appropriation

Cases cited: National Korectailre Company vs. State of Illinois, 22 C.C.R. 302; Gilbert-Hodgman, Inc., vs. State of Illinois, 24 C.C.R. 509

AI-generated summary from the opinion text — may contain errors. The opinion text and PDF above are the official record.

Headnotes

  1. CONTRACTS-lapsed appropriation. Where contract has been properly entered into, all provisions thereof satisfactorily performed, proper charges made therefor, adequate funds wtere available at the time said contract was executed, and the appropriation from which such claim could and would have been paid had lapsed a n award will be made.

Kane County Service Company, claimant, seeks judgment in the sum of $178.49 for 1,630 gallons of No. 2 grade fuel oil delivered to the Department of Public Works and Buildings, Division of Highways, St. Charles Maintenance Storage Building, 1425 South Avenue, St. Charles, Illinois, on March 22, 1967.

The parties have stipulated that “there is lawfully due claimant the sum of $178.49”, and. that said sum would have been paid if claimant’s statement had been filed prior to the close of the biennium.

[*411] Where a contract with the State has been (1)properly entered into; (2) services satisfactorily performed, and materials furnished in accordance with such contract; (3) proper charges made therefor; and, (4) adequate funds were available at the time the contract was entered into, this Court will enter an award for the amount due. National Korectailre Company vs. State of Illinois, 22 C.C.R. 302; Gilbert-Hodgman, Inc., vs. State of Illinois, 24 C.C.R. 509. It appears from the record that all of the qualifications have been met in the instant case.

Claimant is hereby awarded the sum of $178.49.

Official volume 26 (Containing cases in which opinions were filed and orders of dismissal entered, without opinion between: January 10, 1967–June 20, 1969)  ·  All opinions in this volume  ·  Also on CourtListener

This text is OCR/derived from the official volume and may contain errors. The PDF is authoritative. Boundary pages shared with the adjacent opinion are reproduced whole, so the page image may show a neighbor's opening or closing lines; the transcript text itself is opinion-scoped. See About & sources.

Report an error in this opinion